A&R Logo

Black Angel Project

 


Project Overview

   

The Black Angel project is the main focus of Angus & Ross plc. The objective of the project is to re-open the Black Angel zinc mine in West Greenland and to conduct extensive exploration of its 187 km2 licence area aimed at discovery of a significant zinc/lead orebody (“The New Black Angel”).
Black Angel Mountain
In May 2005 the Company commissioned Wardell-Armstrong International to conduct a pre-feasibility study examining the possibility of re-opening the mine as well as assessing the exploration potential of the licence area. The study took over 6 months to complete and included 3 site visits lasting nearly a month. The mine was subjected to a 5-day long inspection by a team of 6 experts, including the mine's former Chief Geologist and former Rock Mechanic.

The study concluded that there is a strong economic case for re-opening the mine and that the likelihood of finding additional ore is high. The main economic indicators from the study are shown in a table below.

Tonnes of
ore (mill feed)
Net Present
Value (10%)*
NPV/share**
IRR
Capex
Base Case
995,000
$52m
33p
35%
$38m
Improved Case
2,166,000
$189m
119p
56%
$47m

* prices used Zn=$1950/t and Pb=$1100/t ** assuming 89.9m shares in issue

Over 1.7 million tons of ore have been classified as “proven reserve” according to the JORC standard, with a further 0.6 million in the “probable reserve” category. The grade of ore would be respectively 9.7% Zn, 3.1% Pb, 21g/t Ag for “proven” and 8.0% Zn, 2.0% Pb, 21g/t Ag for “probable” allowing for a significant dilution (inclusion of a waste rock) reaching 54%. This dilution is to be removed by adding a Dense Media Separation unit at the beginning of processing thus providing the mill with 995,000 tonnes of pure ore containing 17.1% Zn, 5.5%Pb, and 37g/t Ag.

The "Base Case" assumes that only the pillars from the old mine are mined, and only those belonging to the "proven" category (i.e. is based on 1.7m tonnes of ore). The "Improved Case" assumes that in addition to the pillars new ore is found nearby, that could be processed together with the ore from the pillars.

Bringing more ore into the “proven” category improves the economics of the project dramatically (see table). This additional ore can come from the current “probable” category and/or from new discoveries. Angus & Ross plc launched a major exploration programme in 2006 to find the additional ore to meet the target of the "Improved Case". Find out more about our progress on the Development Concept page and the Latest News page.

 

BLACK ANGEL LINKS & NEWS  

QUICK LINKS

 


   
Motzfeldt-mono
Design by AP Zemek, London